Tassajara Hills pipeline project in Dublin slated for late summer

Work will take about 2 months, be limited to daytime hours

The Dublin San Ramon Services District (DSRSD) is preparing to construct an underground pipeline at the northern end of Dublin this summer, ensuring that about 300 homes in the area still have a "redundant potable water supply" and backup service in the event of an emergency.

A pipeline will be extended from an unpaved portion of Cydonia Court to an access road behind Delamar Drive in the Tassajara Hills development where construction is still underway, with another 80 homes remaining to be built, according to DSRSD spokesperson Lea Blevins.

Blevins told the Weekly that the pipeline will allow the district to create a loop in the water system for emergency service to several hundred homes in the neighborhood.

Approximately 1,110 feet of high-density polyethylene pipeline measuring 8 inches in diameter will be installed, then connected to an existing 10-inch-diameter pipeline within an unpaved extension that is within an existing pipeline within Delamar Drive. Around 800 feet of the new pipeline will be installed using horizontal directional drilling, which involves drilling an underground tunnel and pulling the pipeline through the tunnel.

Standard open trench construction in existing graded areas "associated with residential development" will serve as the site for where the remaining 300 feet or so of pipeline will be laid.

What's local journalism worth to you?

Support PleasantonWeekly.com for as little as $5/month.

Join

Work is expected to begin in late summer and last about two months, according to Blevins. Homes near the southeast end of Delamar Drive may be affected by excavation and road repair, and all work will be limited to daytime hours allowed by the city of Dublin.

As part of the planning process, DSRSD recently wrapped up an initial study and mitigated negative declaration (IS/MND), in accordance with the California Environmental Quality Act (CEQA).

Written comments on the IS/MND are being accepted through April 30. Comments may be submitted either to Jaclyn Lee at the DSRSD offices in Dublin: 7051 Dublin Boulevard, 94568, or by emailing [email protected] or calling 875-2258. Due to the ongoing pandemic, the district office is currently closed to the public.

To review the IS/MND, visit www.dsrsd.com. To request additional accommodation to review the IS/MND, contact Jaclyn Yee at the email or phone number provided.

Stay informed

Get daily headlines sent straight to your inbox.

Sign up

Follow PleasantonWeekly.com and the Pleasanton Weekly on Twitter @pleasantonnews, Facebook and on Instagram @pleasantonweekly for breaking news, local events, photos, videos and more.

Tassajara Hills pipeline project in Dublin slated for late summer

Work will take about 2 months, be limited to daytime hours

by / Pleasanton Weekly

Uploaded: Thu, Apr 8, 2021, 4:30 pm

The Dublin San Ramon Services District (DSRSD) is preparing to construct an underground pipeline at the northern end of Dublin this summer, ensuring that about 300 homes in the area still have a "redundant potable water supply" and backup service in the event of an emergency.

A pipeline will be extended from an unpaved portion of Cydonia Court to an access road behind Delamar Drive in the Tassajara Hills development where construction is still underway, with another 80 homes remaining to be built, according to DSRSD spokesperson Lea Blevins.

Blevins told the Weekly that the pipeline will allow the district to create a loop in the water system for emergency service to several hundred homes in the neighborhood.

Approximately 1,110 feet of high-density polyethylene pipeline measuring 8 inches in diameter will be installed, then connected to an existing 10-inch-diameter pipeline within an unpaved extension that is within an existing pipeline within Delamar Drive. Around 800 feet of the new pipeline will be installed using horizontal directional drilling, which involves drilling an underground tunnel and pulling the pipeline through the tunnel.

Standard open trench construction in existing graded areas "associated with residential development" will serve as the site for where the remaining 300 feet or so of pipeline will be laid.

Work is expected to begin in late summer and last about two months, according to Blevins. Homes near the southeast end of Delamar Drive may be affected by excavation and road repair, and all work will be limited to daytime hours allowed by the city of Dublin.

As part of the planning process, DSRSD recently wrapped up an initial study and mitigated negative declaration (IS/MND), in accordance with the California Environmental Quality Act (CEQA).

Written comments on the IS/MND are being accepted through April 30. Comments may be submitted either to Jaclyn Lee at the DSRSD offices in Dublin: 7051 Dublin Boulevard, 94568, or by emailing [email protected] or calling 875-2258. Due to the ongoing pandemic, the district office is currently closed to the public.

To review the IS/MND, visit www.dsrsd.com. To request additional accommodation to review the IS/MND, contact Jaclyn Yee at the email or phone number provided.

Comments

There are no comments yet. Please share yours below.

Post a comment

In order to encourage respectful and thoughtful discussion, commenting on stories is available to those who are registered users. If you are already a registered user and the commenting form is not below, you need to log in. If you are not registered, you can do so here.

Please make sure your comments are truthful, on-topic and do not disrespect another poster. Don't be snarky or belittling. All postings are subject to our TERMS OF USE, and may be deleted if deemed inappropriate by our staff.

See our announcement about requiring registration for commenting.