Caltrans inspectors last month found a damaged seismic expansion joint showing signs of premature wear on the westbound side of the Carquinez Bridge, agency officials said Thursday.

During an inspection of the suspension bridge on May 15, inspectors saw that that one of its expansion joints was cracked and misaligned and that one of the 90 pivot pins holding it in place had slipped loose from its bearing, according to Caltrans spokesman Bob Haus.

When the pivot pin came loose, it damaged other components of the seismic joint in the process, including a neoprene stirrup bearing and two plate bearings, Haus said.

The spokesman said inspectors first noticed that the joint was "slightly misaligned" during an inspection in September 2012, but thought the misalignment might be repaired as part of a longer-term bridge upgrade.

But after seeing the damage to the joint in May, Caltrans crews made temporary repairs to shore it up and ensure it is fully operational, Haus said.

"There's no danger to the traveling public at all," he said.

Haus said Caltrans is working on plans to repair the joint and adjoining components damaged by the loosened pivot pin. He said he did not have an estimate for the repair project but said it would likely cost hundreds of thousands of dollars.

The seismic joint affected is one of two expansion joints on the westbound span of the Carquinez Bridge, also known as the Al Zampa Memorial Bridge, which opened in 2003 after a $500 million construction project and connects Vallejo to Crockett.

The accordion-like component is designed to absorb movement and includes pivot pins meant to give the bridge the flexibility it needs to stay intact both during everyday traffic and in the event of an earthquake.

The damaged joint is located along a slow lane of traffic -- the part of the bridge that is most heavily traveled by large trucks.

"All signs point to this area being affected by truck traffic and we know that trucks place greater stress on transportation infrastructure,"

said John Goodwin of the Metropolitan Transportation Commission, which discussed the seismic joint problem at a meeting on Wednesday.

When the Carquinez Bridge's new span was built over a decade ago, its joint system was projected to last for about 20 years before needing to be replaced, Goodwin said.

"Now we're at 11.5 years after opening," he said.

— Bay City News Service

Comments

There are no comments yet. Please share yours below.

Post a comment

Posting an item on Town Square is simple and requires no registration. Just complete this form and hit "submit" and your topic will appear online. Please be respectful and truthful in your postings so Town Square will continue to be a thoughtful gathering place for sharing community information and opinion. All postings are subject to our TERMS OF USE, and may be deleted if deemed inappropriate by our staff.

We prefer that you use your real name, but you may use any "member" name you wish.

Name: *

Select your neighborhood or school community: *

Choose a category: *

Since this is the first comment on this story a new topic will also be started in Town Square! Please choose a category that best describes this story.

Comment: *

Verification code: *
Enter the verification code exactly as shown, using capital and lowercase letters, in the multi-colored box.

*Required Fields

Martin Litton, force of nature. An appreciation.
By Tom Cushing | 2 comments | 1,050 views

What to do with your buckets of water
By Tim Hunt | 3 comments | 755 views

The Golden Days of Television
By Roz Rogoff | 0 comments | 532 views

How Many Colleges Should I Apply To?
By Elizabeth LaScala | 0 comments | 315 views